Constructed in an environmentally sensitive wetland, this containment system included one mile of cast-in-place concrete.
24,000-cubic yards of concrete were poured in 3 months, using 1,800 tons of rebar.
Constructed in an environmentally sensitive wetland, this containment system included one mile of cast-in-place concrete.
24,000-cubic yards of concrete were poured in 3 months, using 1,800 tons of rebar.